Notes from group meeting Saturday, February 12, 2011
Action Items
Lakita
By 2/15 7:30 pm Group Meeting
- Use 4 survey questions that were created by group and survey the graphic designers on Monday 2/14 to collect data. Ready to report to group on 2/15 and in a report form to present to class on 2/16.
- Determine fonts and colors that will be used for project.
- Upload to dropbox any images, graphics, etc that will be used in project. This includes the Review page screen shots, logos, etc.
By 2/22?
- Meet with department director to determine content for Design page.
- If a video interview of “best practices” is going to be used on Design page, script it out and determine action steps.
- Have a rough draft script of “Worst Case Scenario” so that group can determine action steps for storyboarding and filming.
Steve
By 2/15 7:30 pm Group Meeting
- Create wikispaces site and a basic wireframe for group to look over. Complete any edits to wireframe (NOT completed project) to present to class on 2/16
- Read over the latest design document BSGdesignEDIT3-sjw.docx. Make notes on anything that is not clear or questions you have.
- Search for some images – question marks, clocks ticking, etc. – that can be used. Lakita suggested use www.veer.com
By 2/22?
- Update wikispace with appropriate fonts, colors, images, etc.
Ann
By 2/15 7:30 pm Group Meeting
- Update design document to be version 4. Include the following:
- Accept track changes from 2/10 class meeting
- Clarify in that the purpose of the tutorial is a reminder of best practices, not an introduction to best practices. There is a manual being development for new employees. This tutorial is to be used by graphic designers that have been on the job 6+ months. Note that this was clarified this with department director that this is their direction.
- Tighten up language in Goals & Objectives as well as Learning Activities.
- Create these notes, send them out along with meeting invitation (gotomeeting) to group.
By 2/22?
- Help Steve as needed in terms of working with wikispaces.
- Set up protections on wikispaces so the site is locked, etc.
- Find a couple of appropriate “how to” links on what is/ how to use wikispaces.
- Create example of SWOT analysis, evaluation tools, etc.
- Update design document to version 5.
Proposal
We will work on this as our project 1 and 2 for CECS 5440.
- By March 1 all written content and static images will be in place.
- Videos and slideshows will be complete by March 11.
- Implementation/ Launch no later than Monday, March 14.
- Assessment and Evaluation will take place week of March 21-25
- Final report to class March 31.
Advertisement








Pingback: Week 4 Post « Lakita's Blog